Do not add parallel task durations to predict earliest completion.
Which tasks are sequential and which can overlap in the supplied dependency model?
Use the matching calculator
Use this decision sequence
- List tasks in an order where predecessors appear before dependants.
- Use zero predecessor for independent tasks and an earlier task number for one dependency.
- Calculate each finish from its predecessor’s finish plus entered duration.
- Compare the longest finish with total effort, while keeping resource feasibility outside this simple model.
Keep the quantities distinct
| Quantity or assumption | How to use it |
|---|---|
| Summed durations | Total entered task effort. |
| Dependency completion | Longest finish across task chains. |
| Resource constraint | Not represented by one predecessor and unlimited parallel resources. |
Worked comparison
An illustrative task A lasts three hours, B lasts four hours after A, and C lasts five hours independently. Entered durations sum to 12 hours, but the unconstrained earliest completion is max(3+4,5) = 7 hours. If the same worker must do every task, the seven-hour bound is not a feasible crew schedule; extra resource constraints are needed.
Check before using the estimate
The result is an unconstrained planning bound, not a staffing recommendation or delivery promise.