Subtract the Shared Volume

When two concrete wall runs meet at a right angle, subtract the volume where they occupy the same space if both run lengths include that crossing. In this example, the shared rectangular area is 0.19 m × 1.38 m, and the overlap extends 0.19 m along the adjoining run. That gives a geometric overlap of 0.049818 m³. Deduct it once from the combined segment volumes to avoid counting that concrete twice.

The decision depends on what each length measures. If both measurements extend to the outside faces through the junction, their separate volume calculations include the same block. If one run already stops at the face of the other, its length excludes that block, so subtracting the overlap again would remove concrete that was never counted in that run. Check endpoints on the plan or measurement notes before entering an intersection deduction.

Confirm What Lengths Include

Before calculating, identify each wall segment and mark where its measured length begins and ends. For the published worked example, the two runs measure 3.47 m and 2.94 m. Both use a specified thickness of 190 mm and a height of 1.38 m. The example assigns no opening area to either segment. Those inputs describe rectangular wall runs; the crossing deduction handles their shared portion separately.

Compare the measured endpoints with the adjoining faces. A dimension that reaches through the junction to the far face of the second wall includes the crossing in its run volume. A dimension that ends at the near face does not include material beyond that face. Do not infer this from the drawing's appearance alone: dimension lines, notes, or field measurements determine what the entered lengths count. Resolve any ambiguity before calculating.

Calculate Each Run Volume

For a rectangular wall segment, multiply length by height by thickness after expressing all three dimensions in meters. Here, 190 mm is 0.19 m. The 3.47 m run therefore represents 3.47 m × 1.38 m × 0.19 m, or 0.909834 m³ before the crossing adjustment. The 2.94 m run represents 2.94 m × 1.38 m × 0.19 m, or 0.770868 m³.

Adding those two segment volumes gives 1.680702 m³ before intersections. This is local arithmetic from the stated dimensions, not a separate property of a particular concrete mix. The zero opening areas in the example mean there is no opening-area deduction in these inputs. If your measured wall has openings, enter their areas according to the calculator's fields and make sure the dimensions you enter describe the same wall scope.

Measure the Crossing Block

The shared block's volume comes from its three dimensions: wall thickness, wall height, and the length of overlap along the adjoining run. In this example, each wall has a thickness of 0.19 m and height of 1.38 m, while the overlap depth is 0.19 m. Multiplying 0.19 m × 1.38 m × 0.19 m gives 0.049818 m³. This is the geometric volume counted twice when both runs continue through the junction.

Use dimensions that match the actual intersection shape. The example assumes a rectangular crossing with equal wall thicknesses and a full shared height. The arithmetic describes that defined geometry; it does not establish how a wall should be built or whether a design is suitable. If the segments have different heights, thicknesses, or an irregular junction, establish the shared shape and its dimensions before applying a single rectangular deduction.

Enter the Calculator Inputs

In the Concrete Wall Calculator, enter the two rows from the worked example: Segment length 3.47 m and Segment length 2.94 m; Height 1.38 m for each; Specified thickness 190 mm for each; and Opening area 0 m² for each. Enter Intersection volume counted twice as 0.049818 m³. The calculator accepts the thickness in millimeters as shown, so retain 190 mm in that field rather than converting it to 0.19 m.

The worked example sets Waste allowance to 0%. That setting leaves the computed volume unchanged by an added percentage. Use the same measurement basis for both segments and the overlap deduction: this example uses meters and cubic meters for lengths and volumes, with thickness entered in millimeters because that is the field's displayed unit. Review the entries before calculating, especially the two segment lengths and whether both include the junction.

Read the Adjusted Result

With the example inputs, the Concrete Wall Calculator reports Concrete to order of 1.630884 m³. Its details show Volume before intersections of 1.680702 m³ and Intersection deduction of 0.049818 m³. Subtracting the displayed deduction from the pre-intersection volume reproduces the reported result: 1.680702 m³ − 0.049818 m³ = 1.630884 m³. The title's crossing adjustment is therefore expressed as a volume, not as a length or area.

Interpret that output in light of the inputs. It is the calculator's computed volume after the entered shared block is deducted and the entered waste allowance is applied. With waste set to zero, the example's final result is simply the pre-intersection total less the crossing volume. The result does not independently verify field dimensions; it reflects the measurements and settings entered. Keep those dimensions with the result so the calculation can be reviewed.

Avoid a Second Deduction

Do not enter the 0.049818 m³ deduction if the run lengths already stop at the adjacent wall face and therefore exclude the shared block. In that case, the two rectangular volumes do not both contain the crossing, so a further deduction would lower the calculated total by material that was not double-counted. The calculator cannot determine endpoint conventions from lengths alone; that judgment comes from the dimensions and their intended endpoints.

Likewise, do not subtract the same crossing once from a segment length and again as Intersection volume counted twice. Choose one consistent representation of the measured geometry. In the published example, both full run lengths are entered and the shared volume is deducted once. Compare your own entries against that setup: either both lengths include the crossing and the deduction is entered, or the crossing has already been excluded from a length.

Review Before Using the Figure

Before relying on the total for your quantity worksheet, check that both runs refer to the same wall height and specified thickness throughout the crossing. Confirm whether the 3.47 m and 2.94 m dimensions terminate at outside faces or at the adjoining face, and make sure the entered overlap depth corresponds to the shared block. These are the project-specific measurements that determine whether 0.049818 m³ is the correct deduction for your geometry.

Questions about this guide

When should I enter an intersection deduction?

Enter the shared volume when both wall run lengths extend through the crossing and each run's rectangular volume includes the same block. For the worked example, that shared block is 0.049818 m³.

What if one run stops at the other wall's face?

If that endpoint means the run volume already excludes the shared block, do not subtract the crossing again. Check the dimension endpoints before deciding whether both runs include it.

Why does the worked example report 1.630884 m³?

The two segment volumes total 1.680702 m³ before intersections. Subtracting the 0.049818 m³ intersection deduction, with Waste allowance set to 0%, gives Concrete to order of 1.630884 m³.

Should I use the example's deduction for a differently shaped crossing?

Only if your shared geometry has the same relevant dimensions and rectangular shape. Work out the volume of your actual shared block from its measured dimensions; the example's 0.049818 m³ follows from 0.19 m thickness, 1.38 m height, and 0.19 m overlap depth.

Use the matching calculator

Updated . Reviewed . Methods and scope.

Related decisions

Connected work guides and comparisons

Browse all work types

Collect your material inputs

Browse material preparation sheets

Evaluate your own supplied alternatives

Browse quantity scenarios