Deduct intersections in a supplied concrete rib grid.

Why is the sum of two directions of ribs larger than the actual material?

Use the matching calculator

Use this decision sequence

  1. Calculate the continuous top layer over the entire footprint.
  2. Measure rib depth below that layer, not total top-to-bottom thickness.
  3. Add the volume of each specified full-length rib direction.
  4. Deduct the common volume at every crossing once before combining with the top layer.

Keep the quantities distinct

Quantity or assumptionHow to use it
Top layerContinuous area times top thickness.
Two rib directionsInclude their crossing volumes twice.
Crossing deductionNumber of crossings times both widths times below-top depth.

Worked comparison

A 4 m by 3 m top layer at 0.1 m contains 1.2 m³. Two 0.2 m-wide ribs in each direction, 0.3 m below that layer, add 0.48 + 0.36 = 0.84 m³ before deduction. Four crossings each contain 0.2×0.2×0.3 = 0.012 m³. The reconciled total is 1.2 + 0.84 − 0.048 = 1.992 m³.

Check before using the estimate

Counts, sections and layout must be supplied by the existing design; quantity does not demonstrate structural suitability.

All dimensions, product properties, prices and specifications in this example are illustrative arithmetic inputs. Use the values from your measured plan, selected product data sheet and supplier quote. This guide does not choose construction specifications or certify safety.

Calculation and scope checked 2026-10-04. Methods and scope.

Related decisions

Connected work guides and comparisons

Browse all work types

Collect your material inputs

Browse material preparation sheets

Evaluate your own supplied alternatives

Browse quantity scenarios